HOUSE BILL NO. 741
Offered January 10, 2024
Prefiled January 9, 2024
A BILL to amend and reenact §§ 10.1-1197.5, 10.1-1197.6, 10.1-1197.7, 10.1-1197.8, 10.1-1197.11, 56-46.1, and 56-580 of the Code of Virginia, relating to Department of Environmental Quality; nuclear energy electric generation facilities; permitting.
----------
Patron-- O'Quinn
----------
Referred to Committee on Labor and Commerce
----------

Be it enacted by the General Assembly of Virginia:

1. That §§ 10.1-1197.5, 10.1-1197.6, 10.1-1197.7, 10.1-1197.8, 10.1-1197.11, 56-46.1, and 56-580 of the Code of Virginia are amended and reenacted as follows:

Article 5.
Small Renewable Clean Energy Projects.

§ 10.1-1197.5. Definitions.

As used in this article:

"Energy storage facility" means energy storage equipment or technology that is capable of absorbing energy, storing such energy for a period of time, and redelivering energy after it has been stored.

"Small renewable clean energy project" means (i) an electrical generation facility with a rated capacity not exceeding 150 megawatts that generates electricity only from sunlight or wind; (ii) an electrical generation facility with a rated capacity not exceeding 100 megawatts that generates electricity only from falling water, wave motion, tides, or geothermal power; (iii) an electrical generation facility with a rated capacity not exceeding 20 megawatts that generates electricity only from biomass, energy from waste, or municipal solid waste; (iv) an electrical generation facility with a rated capacity not exceeding 300 megawatts that generates electricity only from nuclear energy located in Planning District 1, 2, 3, or 4; (v) an energy storage facility that uses electrochemical cells to convert chemical energy with a rated capacity not exceeding 150 megawatts; or (v) (vi) a hybrid project composed of an electrical generation facility that meets the parameters established in clause (i), (ii), or (iii), or (iv) and an energy storage facility that meets the parameters established in clause (iv) (v).

§ 10.1-1197.6. Permit by rule for small clean energy projects.

A. Notwithstanding the provisions of § 10.1-1186.2:1, the Department shall develop, by regulations to be effective as soon as practicable, but not later than July 1, 2012, a permit by rule or permits by rule if it is determined by the Department that one or more such permits by rule are necessary for the construction and operation of small renewable clean energy projects, including such conditions and standards necessary to protect the Commonwealth's natural resources. If the Department determines that more than a single permit by rule is necessary, the Department initially shall develop the permit by rule for wind energy, which shall be effective as soon as practicable, but not later than January 1, 2011. The Department shall develop the permit by rule for nuclear energy, which shall be effective as soon as practicable. Subsequent permits by rule regulations shall be effective as soon as practicable.

B. The conditions for issuance of the permit by rule for small renewable clean energy projects shall include:

1. A notice of intent provided by the applicant, to be published in the Virginia Register, that a person intends to submit the necessary documentation for a permit by rule for a small renewable clean energy project;

2. A certification by the governing body of the locality or localities wherein the small renewable clean energy project will be located that the project complies with all applicable land use ordinances;

3. Copies of all interconnection studies undertaken by the regional transmission organization or transmission owner, or both, on behalf of the small renewable clean energy project;

4. A copy of the final interconnection agreement between the small renewable clean energy project and the regional transmission organization or transmission owner indicating that the connection of the small renewable clean energy project will not cause a reliability problem for the system. If the final agreement is not available, the most recent interconnection study shall be sufficient for the purposes of this section. When a final interconnection agreement is complete, it shall be provided to the Department. The Department shall forward a copy of the agreement or study to the State Corporation Commission;

5. A certification signed by a professional engineer licensed in Virginia that the maximum generation capacity of the small renewable clean energy project by (i) an electrical generation facility that generates electricity only from sunlight or wind as designed does not exceed 150 megawatts; (ii) an electrical generation facility that generates electricity only from falling water, wave motion, tides, or geothermal power as designed does not exceed 100 megawatts; or (iii) an electrical generation facility that generates electricity only from biomass, energy from waste, or municipal solid waste as designed does not exceed 20 megawatts; or (iv) an electrical generation facility that generates electricity only from nuclear energy as designed does not exceed 300 megawatts;

6. An analysis of potential environmental impacts of the small renewable clean energy project's operations on attainment of national ambient air quality standards;

7. Where relevant, an analysis of the beneficial and adverse impacts of the proposed project on natural resources. For wildlife, that analysis shall be based on information on the presence, activity, and migratory behavior of wildlife to be collected at the site for a period of time dictated by the site conditions and biology of the wildlife being studied, not exceeding 12 months. For prime agricultural soils and forest land, that analysis shall be required if a proposed project would disturb more than 10 acres of prime agricultural soils or 50 acres of contiguous forest lands, or if it would disturb forest lands enrolled in a program for forestry preservation pursuant to subdivision 2 of § 58.1-3233;

8. If the Department determines that the information collected pursuant to subdivision 7 indicates that significant adverse impacts to wildlife, historic resources, prime agricultural soils, or forest lands are likely, the submission of a mitigation plan, if a draft plan was not provided by the applicant as part of the initial application, with a 45-day public comment period detailing reasonable actions to be taken by the owner or operator to avoid, minimize, or otherwise mitigate such impacts, and to measure the efficacy of those actions. A project will be deemed to have a significant adverse impact if it would disturb more than 10 acres of prime agricultural soils or 50 acres of contiguous forest lands, or if it would disturb forest lands enrolled in a program for forestry preservation pursuant to subdivision 2 of § 58.1-3233;

9. A certification signed by a professional engineer licensed in Virginia that the small renewable clean energy project is designed in accordance with all of the standards that are established in the regulations applicable to the permit by rule;

10. An operating plan describing how any standards established in the regulations applicable to the permit by rule will be achieved;

11. A detailed site plan with project location maps that show the location of all components of the small renewable clean energy project, including any towers. Changes to the site plan that occur after the applicant has submitted an application shall be allowed by the Department without restarting the application process, if the changes were the result of optimizing technical, environmental, and cost considerations, do not materially alter the environmental effects caused by the facility, or do not alter any other environmental permits that the Commonwealth requires the applicant to obtain;

12. A certification signed by the applicant that the small renewable clean energy project has applied for or obtained all necessary environmental permits;

13. A requirement that the applicant hold a public meeting. The public meeting shall be held in the locality or, if the project is located in more than one locality in a place proximate to the location of the proposed project. Following the public meeting, the applicant shall prepare a report summarizing the issues raised at the meeting, including any written comments received. The report shall be provided to the Department; and

14. A 30-day public review and comment period prior to authorization of the project.

C. The Department's regulations shall establish a schedule of fees, to be payable by the owner or operator of the small renewable clean energy project regulated under this article, which fees shall be assessed for the purpose of funding the costs of administering and enforcing the provisions of this article associated with such operations including, but not limited to, the inspection and monitoring of such projects to ensure compliance with this article.

D. The owner or operator of a small renewable clean energy project regulated under this article shall be assessed a permit fee in accordance with the criteria set forth in the Department's regulations. Such fees shall include an additional amount to cover the Department's costs of inspecting such projects.

E. The fees collected pursuant to this article shall be used only for the purposes specified in this article and for funding purposes authorized by this article to abate impairments or impacts on the Commonwealth's natural resources directly caused by small renewable clean energy projects.

F. There is hereby established a special, nonreverting fund in the state treasury to be known as the Small Renewable Clean Energy Project Fee Fund, hereafter referred to as the Fund. Notwithstanding the provisions of § 2.2-1802, all moneys collected pursuant to this § 10.1-1197.6 shall be paid into the state treasury to the credit of the Fund. Any moneys remaining in the Fund shall not revert to the general fund but shall remain in the Fund. Interest earned on such moneys shall remain in the Fund and be credited to it. The Fund shall be exempt from statewide indirect costs charged and collected by the Department of Accounts.

G. After the effective date of regulations adopted pursuant to this section, no person shall erect, construct, materially modify, or operate a small renewable clean energy project except in accordance with this article or Title 56 if the small renewable clean energy project was approved pursuant to Title 56.

H. Any small renewable clean energy project shall be eligible for permit by rule under this section if the project is proposed, developed, constructed, or purchased by a person that is not a utility regulated pursuant to Title 56.

I. Any small renewable clean energy project commencing operations after July 1, 2017, shall be eligible for permits by rule under this section and is exempt from State Corporation Commission environmental review or permitting in accordance with subsection B of § 10.1-1197.8 or other applicable law if the project is proposed, developed, constructed, or purchased by:

1. A public utility if the project's costs are not recovered from Virginia jurisdictional customers under base rates, a fuel factor charge under § 56-249.6, or a rate adjustment clause under subdivision A 6 of § 56-585.1; or

2. A utility aggregation cooperative formed under Article 2 (§ 56-231.38 et seq.) of Chapter 9.1 of Title 56.

J. For purposes of this section, "prime agricultural soils" means soils recognized as prime farmland by the U.S. Department of Agriculture, and "forest land" has the same meaning as provided in § 10.1-1178, except that any parcel shall be considered forest lands if it was forested at least two years prior to the Department's receipt of a permit application.

§ 10.1-1197.7. Review and authorization of projects.

A. Upon submission of a complete application, the Department, after consultation with other agencies in the Secretariat of Natural and Historic Resources before authorizing the project, shall conduct an assessment of whether the application meets the requirements of the applicable permit by rule regulations. If the Department determines that the application is deficient, it promptly shall notify the applicant in writing and specify the deficiencies.

B. Any interested party, including an applicant for a permit, who has participated in a proceeding for a permit to construct or operate a small renewable clean energy project under procedures adopted by the Department pursuant to this section, and who is aggrieved by the final decision of the Department, shall have the remedies provided by the Administrative Process Act (§ 2.2-4000 et seq.).

§ 10.1-1197.8. Limitation of State Corporation Commission authority.

A. If the owner or operator of a small renewable clean energy project to whom the Department has authorized a permit by rule pursuant to this article is not a utility regulated pursuant to Title 56, then the State Corporation Commission shall not have jurisdiction to review the small renewable clean energy project or to condition the construction or operation of a small renewable clean energy project upon the State Corporation Commission's issuance of any permit or certificate under any provision of Title 56, provided that the State Corporation Commission shall retain jurisdiction to resolve requests for joint use of the rights of way of public service corporations pursuant to § 56-259 and denials of requests for interconnection of facilities pursuant to § 56-578.

B. If the owner or operator of a small renewable clean energy project for which the Department has authorized a permit by rule pursuant to this article is a utility regulated pursuant to Title 56, such small renewable clean energy project shall be exempt from any provision of § 56-46.1 and any corresponding provision of subsection D of § 56-580 or Chapter 10.1 (§ 56-265.1 et seq.) of Title 56 that requires environmental review and permitting by the State Corporation Commission. An owner or operator of a small renewable clean energy project that is granted a permit by rule pursuant to subsection I of § 10.1-1197.6, shall not be required to obtain a certificate of public convenience and necessity pursuant to subsection D of § 56-580 or the Utility Facilities Act (§ 56-265.1 et seq.). Nothing in this section shall affect the jurisdiction of the State Corporation Commission regarding a utility that is not eligible for a permit by rule, or the requirement of such utility to obtain a certificate of public convenience and necessity.

§ 10.1-1197.11. Information to be furnished to Department.

Except as otherwise specified in this article, the Department may require every owner or operator of a small renewable clean energy project to furnish when requested such plans, specifications, and other pertinent information as may be necessary to determine the compliance status of the project and the effect of the project on human health or the environment.

§ 56-46.1. Commission to consider environmental, economic, and improvements in service reliability factors in approving construction of electrical utility facilities; approval required for construction of certain electrical transmission lines; notice and hearings.

A. Whenever the Commission is required to approve the construction of any electrical utility facility, it shall give consideration to the effect of that facility on the environment and establish such conditions as may be desirable or necessary to minimize adverse environmental impact. In order to avoid duplication of governmental activities, any valid permit or approval required for an electric generating plant and associated facilities issued or granted by a federal, state, or local governmental entity charged by law with responsibility for issuing permits or approvals regulating environmental impact and mitigation of adverse environmental impact or for other specific public interest issues such as building codes, transportation plans, and public safety, whether such permit or approval is granted prior to or after the Commission's decision, shall be deemed to satisfy the requirements of this section with respect to all matters that (i) are governed by the permit or approval or (ii) are within the authority of, and were considered by, the governmental entity in issuing such permit or approval, and the Commission shall impose no additional conditions with respect to such matters. Nothing in this section shall affect the ability of the Commission to keep the record of a case open. Nothing in this section shall affect any right to appeal such permits or approvals in accordance with applicable law. In the case of a proposed facility located in a region that was designated as of July 1, 2001, as serious nonattainment for the one-hour ozone standard as set forth in the federal Clean Air Act, the Commission shall not issue a decision approving such proposed facility that is conditioned upon issuance of any environmental permit or approval. In every proceeding under this subsection, the Commission shall receive and give consideration to all reports that relate to the proposed facility by state agencies concerned with environmental protection; and if requested by any county or municipality in which the facility is proposed to be built, to local comprehensive plans that have been adopted pursuant to Article 3 (§ 15.2-2223 et seq.) of Chapter 22 of Title 15.2. Additionally, the Commission (a) shall consider the effect of the proposed facility on economic development within the Commonwealth, including but not limited to furtherance of the economic and job creation objectives of the Commonwealth Clean Energy Policy set forth in § 45.2-1706.1, and (b) shall consider any improvements in service reliability that may result from the construction of such facility.

B. Subject to the provisions of subsection J, no electrical transmission line of 138 kilovolts or more shall be constructed unless the State Corporation Commission shall, after at least 30 days' advance notice by (i) publication in a newspaper or newspapers of general circulation in the counties and municipalities through which the line is proposed to be built, (ii) written notice to the governing body of each such county and municipality, and (iii) causing to be sent a copy of the notice by first class mail to all owners of property within the route of the proposed line, as indicated on the map or sketch of the route filed with the Commission, which requirement shall be satisfied by mailing the notice to such persons at such addresses as are indicated in the land books maintained by the commissioner of revenue, director of finance or treasurer of the county or municipality, approve such line. Such notices shall include a written description of the proposed route the line is to follow, as well as a map or sketch of the route including a digital geographic information system (GIS) map provided by the public utility showing the location of the proposed route. The Commission shall make GIS maps provided under this subsection available to the public on the Commission's website. Such notices shall be in addition to the advance notice to the chief administrative officer of the county or municipality required pursuant to § 15.2-2202.

As a condition to approval, the Commission shall determine that the line is needed and that the corridor or route chosen for the line will avoid or reasonably minimize adverse impact to the greatest extent reasonably practicable on the scenic assets, historic resources recorded with the Department of Historic Resources, and environment of the area concerned. To assist the Commission in this determination, as part of the application for Commission approval of the line, the applicant shall summarize its efforts to avoid or reasonably minimize adverse impact to the greatest extent reasonably practicable on the scenic assets, historic resources recorded with the Department of Historic Resources, and environment of the area concerned. In making the determinations about need, corridor or route, and method of installation, the Commission shall verify the applicant's load flow modeling, contingency analyses, and reliability needs presented to justify the new line and its proposed method of installation. If the local comprehensive plan of an affected county or municipality designates corridors or routes for electric transmission lines and the line is proposed to be constructed outside such corridors or routes, in any hearing the county or municipality may provide adequate evidence that the existing planned corridors or routes designated in the plan can adequately serve the needs of the company. Additionally, the Commission shall consider, upon the request of the governing body of any county or municipality in which the line is proposed to be constructed, (a) the costs and economic benefits likely to result from requiring the underground placement of the line and (b) any potential impediments to timely construction of the line.

C. If, prior to such approval, any interested party shall request a public hearing, the Commission shall, as soon as reasonably practicable after such request, hold such hearing or hearings at such place as may be designated by the Commission. In any hearing the public service company shall provide adequate evidence that existing rights-of-way cannot adequately serve the needs of the company.

If, prior to such approval, written requests therefor are received from the governing body of any county or municipality through which the line is proposed to be built or from 20 or more interested parties, the Commission shall hold at least one hearing in the area that would be affected by construction of the line, for the purpose of receiving public comment on the proposal. If any hearing is to be held in the area affected, the Commission shall direct that a copy of the transcripts of any previous hearings held in the case be made available for public inspection at a convenient location in the area for a reasonable time before such local hearing.

D. As used in this section, unless the context requires a different meaning:

"Environment" or "environmental" shall be deemed to include in meaning "historic," as well as a consideration of the probable effects of the line on the health and safety of the persons in the area concerned.

"Interested parties" shall include the governing bodies of any counties or municipalities through which the line is proposed to be built, and persons residing or owning property in each such county or municipality.

"Public utility" means a public utility as defined in § 56-265.1.

"Qualifying facilities" means a cogeneration or small power production facility which meets the criteria of 18 C.F.R. Part 292.

"Reasonably accommodate requests to wheel or transmit power" means:

1. That the applicant will make available to new electric generation facilities constructed after January 9, 1991, qualifying facilities and other nonutilities, a minimum of one-fourth of the total megawatts of the additional transmission capacity created by the proposed line, for the purpose of wheeling to public utility purchasers the power generated by such qualifying facilities and other nonutility facilities which are awarded a power purchase contract by a public utility purchaser in compliance with applicable state law or regulations governing bidding or capacity acquisition programs for the purchase of electric capacity from nonutility sources, provided that the obligation of the applicant will extend only to those requests for wheeling service made within the 12 months following certification by the State Corporation Commission of the transmission line and with effective dates for commencement of such service within the 12 months following completion of the transmission line; and

2. That the wheeling service offered by the applicant, pursuant to subdivision D 1, will reasonably further the purposes of the Public Utilities Regulatory Policies Act of 1978 (P. L. 95-617), as demonstrated by submitting to the Commission, with its application for approval of the line, the cost methodologies, terms, conditions, and dispatch and interconnection requirements the applicant intends, subject to any applicable requirements of the Federal Energy Regulatory Commission, to include in its agreements for such wheeling service.

E. In the event that, at any time after the giving of the notice required in subsection B, it appears to the Commission that consideration of a route or routes significantly different from the route described in the notice is desirable, the Commission shall cause notice of the new route or routes to be published and mailed in accordance with subsection B. The Commission shall thereafter comply with the provisions of this section with respect to the new route or routes to the full extent necessary to give affected localities and interested parties in the newly affected areas the same protection afforded to affected localities and interested parties affected by the route described in the original notice.

F. Approval of a transmission line pursuant to this section shall be deemed to satisfy the requirements of § 15.2-2232 and local zoning ordinances with respect to such transmission line.

G. The Commission shall enter into a memorandum of agreement with the Department of Environmental Quality regarding the coordination of their reviews of the environmental impact of electric generating plants and associated facilities.

H. An applicant that is required to obtain (i) a certificate of public convenience and necessity from the Commission for any electric generating facility, electric transmission line, natural or manufactured gas transmission line as defined in 49 Code of Federal Regulations § 192.3, or natural or manufactured gas storage facility (hereafter, an energy facility) and (ii) an environmental permit for the energy facility that is subject to issuance by any agency or board within the Secretariat of Natural and Historic Resources, may request a pre-application planning and review process. In any such request to the Commission or the Secretariat of Natural and Historic Resources, the applicant shall identify the proposed energy facility for which it requests the pre-application planning and review process. The Commission, the Department of Environmental Quality, the Marine Resources Commission, the Department of Wildlife Resources, the Department of Historic Resources, the Department of Conservation and Recreation, and other appropriate agencies of the Commonwealth shall participate in the pre-application planning and review process. Participation in such process shall not limit the authority otherwise provided by law to the Commission or other agencies or boards of the Commonwealth. The Commission and other participating agencies of the Commonwealth may invite federal and local governmental entities charged by law with responsibility for issuing permits or approvals to participate in the pre-application planning and review process. Through the pre-application planning and review process, the applicant, the Commission, and other agencies and boards shall identify the potential impacts and approvals that may be required and shall develop a plan that will provide for an efficient and coordinated review of the proposed energy facility. The plan shall include (a) a list of the permits or other approvals likely to be required based on the information available, (b) a specific plan and preliminary schedule for the different reviews, (c) a plan for coordinating those reviews and the related public comment process, and (d) designation of points of contact, either within each agency or for the Commonwealth as a whole, to facilitate this coordination. The plan shall be made readily available to the public and shall be maintained on a dedicated website to provide current information on the status of each component of the plan and each approval process including opportunities for public comment.

I. The provisions of this section shall not apply to the construction and operation of a small renewable clean energy project, as defined in § 10.1-1197.5, by a utility regulated pursuant to this title for which the Department of Environmental Quality has issued a permit by rule pursuant to Article 5 (§ 10.1-1197.5 et seq.) of Chapter 11.1 of Title 10.1.

J. Approval under this section shall not be required for any transmission line for which a certificate of public convenience and necessity is not required pursuant to subdivision A of § 56-265.2.

§ 56-580. Transmission and distribution of electric energy.

A. Subject to the provisions of § 56-585.1, the Commission shall continue to regulate pursuant to this title the distribution of retail electric energy to retail customers in the Commonwealth and, to the extent not prohibited by federal law, the transmission of electric energy in the Commonwealth.

B. The Commission shall continue to regulate, to the extent not prohibited by federal law, the reliability, quality and maintenance by transmitters and distributors of their transmission and retail distribution systems.

C. The Commission shall develop codes of conduct governing the conduct of incumbent electric utilities and affiliates thereof when any such affiliates provide, or control any entity that provides, generation, distribution, or transmission services, to the extent necessary to prevent impairment of competition. Nothing in this chapter shall prevent an incumbent electric utility from offering metering options to its customers.

D. The Commission shall permit the construction and operation of electrical generating facilities in Virginia upon a finding that such generating facility and associated facilities (i) will have no material adverse effect upon reliability of electric service provided by any regulated public utility, (ii) are required by the public convenience and necessity, if a petition for such permit is filed after July 1, 2007, and if they are to be constructed and operated by any regulated utility whose rates are regulated pursuant to § 56-585.1, and (iii) are not otherwise contrary to the public interest. In review of a petition for a certificate to construct and operate a generating facility described in this subsection, the Commission shall give consideration to the effect of the facility and associated facilities on the environment and establish such conditions as may be desirable or necessary to minimize adverse environmental impact as provided in § 56-46.1, unless exempt as a small renewable clean energy project for which the Department of Environmental Quality has issued a permit by rule pursuant to Article 5 (§ 10.1-1197.5 et seq.) of Chapter 11.1 of Title 10.1. In order to avoid duplication of governmental activities, any valid permit or approval required for an electric generating plant and associated facilities issued or granted by a federal, state or local governmental entity charged by law with responsibility for issuing permits or approvals regulating environmental impact and mitigation of adverse environmental impact or for other specific public interest issues such as building codes, transportation plans, and public safety, whether such permit or approval is prior to or after the Commission's decision, shall be deemed to satisfy the requirements of this section with respect to all matters that (i) are governed by the permit or approval or (ii) are within the authority of, and were considered by, the governmental entity in issuing such permit or approval, and the Commission shall impose no additional conditions with respect to such matters. Nothing in this section shall affect the ability of the Commission to keep the record of a case open. Nothing in this section shall affect any right to appeal such permits or approvals in accordance with applicable law. In the case of a proposed facility located in a region that was designated as of July 1, 2001, as serious nonattainment for the one-hour ozone standard as set forth in the federal Clean Air Act, the Commission shall not issue a decision approving such proposed facility that is conditioned upon issuance of any environmental permit or approval. The Commission shall complete any proceeding under this section, or under any provision of the Utility Facilities Act (§ 56-265.1 et seq.), involving an application for a certificate, permit, or approval required for the construction or operation by a public utility of a small renewable clean energy project as defined in § 10.1-1197.5, within nine months following the utility's submission of a complete application therefore. Small renewable clean energy projects as defined in § 10.1-1197.5 are in the public interest and in determining whether to approve such project, the Commission shall liberally construe the provisions of this title.

E. Nothing in this section shall impair the distribution service territorial rights of incumbent electric utilities, and incumbent electric utilities shall continue to provide distribution services within their exclusive service territories as established by the Commission. Subject to the provisions of § 56-585.1, the Commission shall continue to exercise its existing authority over the provision of electric distribution services to retail customers in the Commonwealth including, but not limited to, the authority contained in Chapters 10 (§ 56-232 et seq.) and 10.1 (§ 56-265.1 et seq.) of this title.

F. Nothing in this chapter shall impair the exclusive territorial rights of an electric utility owned or operated by a municipality as of July 1, 1999, or by an authority created by a governmental unit exempt from the referendum requirement of § 15.2-5403. Nor shall any provision of this chapter apply to any such electric utility unless (i) that municipality or that authority created by a governmental unit exempt from the referendum requirement of § 15.2-5403 elects to have this chapter apply to that utility or (ii) that utility, directly or indirectly, sells, offers to sell or seeks to sell electric energy to any retail customer eligible to purchase electric energy from any supplier in accordance with § 56-577 if that retail customer is outside the geographic area that was served by such municipality as of July 1, 1999, except (a) any area within the municipality that was served by an incumbent public utility as of that date but was thereafter served by an electric utility owned or operated by a municipality or by an authority created by a governmental unit exempt from the referendum requirement of § 15.2-5403 pursuant to the terms of a franchise agreement between the municipality and the incumbent public utility, or (b) where the geographic area served by an electric utility owned or operated by a municipality is changed pursuant to mutual agreement between the municipality and the affected incumbent public utility in accordance with § 56-265.4:1. If an electric utility owned or operated by a municipality as of July 1, 1999, or by an authority created by a governmental unit exempt from the referendum requirement of § 15.2-5403 is made subject to the provisions of this chapter pursuant to clause (i) or (ii) of this subsection, then in such event the provisions of this chapter applicable to incumbent electric utilities shall also apply to any such utility, mutatis mutandis.

G. The applicability of all provisions of this chapter except § 56-594 to any investor-owned incumbent electric utility supplying electric service to retail customers on January 1, 2003, whose service territory assigned to it by the Commission is located entirely within Dickenson, Lee, Russell, Scott, and Wise Counties shall be suspended effective July 1, 2003, so long as such utility does not provide retail electric services in any other service territory in any jurisdiction to customers who have the right to receive retail electric energy from another supplier. During any such suspension period, the utility's rates shall be (i) its capped rates established pursuant to § 56-582 for the duration of the capped rate period established thereunder, and (ii) determined thereafter by the Commission on the basis of such utility's prudently incurred costs pursuant to Chapter 10 (§ 56-232 et seq.) of this title.

H. The expiration date of any certificates granted by the Commission pursuant to subsection D, for which applications were filed with the Commission prior to July 1, 2002, shall be extended for an additional two years from the expiration date that otherwise would apply.

2. That the Department of Environmental Quality shall limit the permitting of an electrical generation facility that generates electricity only from nuclear energy as designed does not exceed 300 megawatts to Planning Districts 1, 2, 3, and 4.