HOUSE BILL NO. 1108
Offered January 10, 2024
Prefiled January 10, 2024
A BILL to amend and reenact §§ 2.2-4380 through 2.2-4383 of the Code of Virginia, relating to Virginia Public Procurement Act; construction management and design-build contracting.
----------
Patrons-- Carr, Sickles, Lopez and Wiley
----------
Referred to Committee on General Laws
----------

Be it enacted by the General Assembly of Virginia:

1. That §§ 2.2-4380 through 2.2-4383 of the Code of Virginia are amended and reenacted as follows:

§ 2.2-4380. Construction management or design-build contracts for state public bodies authorized.

A. Any state public body may enter into a contract for construction on a fixed price or not-to-exceed price construction management or design-build basis, provided that (i) the project is a complex project, (ii) such public body complies with the requirements of this article, and (iii) such public body complies with the procedures adopted by the Secretary of Administration for using construction management or design-build contracts.

B. Procedures adopted by a state public body pursuant to this article shall include the following requirements:

1. A written determination is made in advance by the state public body that competitive sealed bidding is not practicable or fiscally advantageous, and such writing shall document the basis for the determination to use construction management or design-build, including the determination of the project's complexity. The determination shall be included in the Request for Qualifications and maintained in the procurement file;

2. Prior to making a determination as to the use of construction management or design-build for a specific construction project, a state public body shall have in its employ or under contract a licensed architect or engineer with professional competence appropriate to the project who shall (i) advise the public body regarding the use of construction management or design-build for that project and (ii) assist the public body with the preparation of the Request for Proposal and the evaluation of such proposals;

3. Public notice of the Request for Qualifications is posted on the Department's central electronic procurement website, known as eVA, at least 30 days prior to the date set for receipt of qualification proposals;

4. For construction management contracts, the contract is entered into no later than the completion of the schematic phase of design, unless prohibited by authorization of funding restrictions;

5. Prior construction management or design-build experience or previous experience with the Department's Bureau of Capital Outlay Management shall not be required considered as a prerequisite or factor for award of a contract. However, in the selection of a contractor, a state public body may consider the experience of each contractor on comparable projects;

6. Construction management contracts shall require that (i) no more than 10 percent of the construction work, as measured by the cost of the work, be performed by the construction manager with its own forces and (ii) the remaining 90 percent of the construction work, as measured by the cost of the work, be performed by subcontractors of the construction manager, which the construction manager shall procure by publicly advertised, competitive sealed bidding to the maximum extent practicable; and

7. The procedures allow for a two-step competitive negotiation process; and

8. The procedures require the state public body to provide documentation of the processes used for the final selection to all the unsuccessful proposers, upon request.

C. The Department shall evaluate the proposed procurement method selected by the state public body and make its recommendation as to whether the use of the construction management or design-build procurement method is appropriate for the specific project. In its review, the Department shall also consider:

1. The written determination of the state public body;

2. The compliance by the state public body with subdivisions B 1, 2, and 7;

3. The project cost, expected timeline, and use;

4. Whether the project is a complex project; and

5. Any other criteria established by the Department to evaluate the proposed procurement method for the project.

D. The Department shall conduct its review within five working days after receipt of the written determination and render its written recommendation within such five-working-day period. The written recommendation of the Department shall be maintained in the procurement file.

E. If a state public body elects to proceed with the project using a construction management or design-build procurement method despite the recommendation of the Department to the contrary, such state public body shall state in writing its reasons therefor and any justification for not following the recommendation of the Department and submit same to the Department. The written statement of a state public body's decision to not follow the recommendation of the Department shall be maintained in the procurement file.

§ 2.2-4381. Construction management or design-build contracts for covered institutions authorized.

A. Any covered institution may enter into a contract for construction on a fixed price or not-to-exceed price construction management or design-build basis, provided that (i) the project is a complex project, (ii) such institution complies with the requirements of this article, and (iii) such institution complies with the procedures adopted by the Secretary of Administration for using construction management or design-build contracts.

B. Covered institutions shall:

1. Develop procedures for determining the selected procurement method which, at a minimum, shall consider cost, schedule, complexity, and building use;

2. Submit such procedures, and any subsequent changes to adopted procedures, to the Department for review and comment; and

3. Post all documents exchanged between the covered institution and the Department on the Department's central electronic procurement website, known as eVA, prior to the date of submission of proposals; and

4. Submit Department-reviewed procedures to its board of visitors or governing board for adoption.

C. Procedures adopted by a board of visitors pursuant to this article shall include the following requirements:

1. A written determination is made in advance by the covered institution that competitive sealed bidding is not practicable or fiscally advantageous, and such writing shall document the basis for the determination to use construction management or design-build, including the determination of the project's complexity. The determination shall be included in the Request for Qualifications and maintained in the procurement file;

2. Prior to making a determination as to the use of construction management or design-build for a specific construction project, a covered institution shall have in its employ or under contract a licensed architect or engineer with professional competence appropriate to the project who shall (i) advise the covered institution regarding the use of construction management or design-build for that project and (ii) assist the covered institution with the preparation of the Request for Proposal and the evaluation of such proposals;

3. Public notice of the Request for Qualifications is posted on the Department's central electronic procurement website, known as eVA, at least 30 days prior to the date set for receipt of qualification proposals;

4. For construction management contracts, the contract is entered into no later than the completion of the schematic phase of design, unless prohibited by authorization of funding restrictions;

5. Prior construction management or design-build experience or previous experience with the Department's Bureau of Capital Outlay Management shall not be required considered as a prerequisite or factor for award of a contract. However, in the selection of a contractor, a covered institution may consider the experience of each contractor on comparable projects;

6. Construction management contracts shall require that (i) no more than 10 percent of the construction work, as measured by the cost of the work, be performed by the construction manager with its own forces and (ii) the remaining 90 percent of the construction work, as measured by the cost of the work, be performed by subcontractors of the construction manager, which the construction manager shall procure by publicly advertised, competitive sealed bidding to the maximum extent practicable; and

7. The procedures allow for a two-step competitive negotiation process; and

8. The procedures require the covered institution to provide documentation of the processes used for the final selection to all the unsuccessful proposers, upon request.

D. The Department shall evaluate the proposed procurement method selected by a covered institution and make its recommendation as to whether the use of the construction management or design-build procurement method is appropriate for the specific project. In its review, the Department shall also consider:

1. The written determination of the covered institution;

2. The compliance by the covered institution with subdivisions C 1, 2, and 7;

3. The project cost, expected timeline, and use;

4. Whether the project is a complex project; and

5. Any other criteria established by the Department to evaluate the proposed procurement method for the project.

E. The Department shall conduct its review within five working days after receipt of the written determination and render its written recommendation within such five-working-day period. The written recommendation of the Department shall be maintained in the procurement file.

F. If a covered institution elects to proceed with the project using a construction management or design-build procurement method despite the recommendation of the Department to the contrary, such covered institution shall state in writing its reasons therefor and any justification for not following the recommendation of the Department and, submit same to the Department, and secure approval from the board of visitors or governing board of the covered institution. The written statement of a covered institution's decision to not follow the recommendation of the Department and the vote of the board of visitors or governing board shall be maintained in the procurement file.

§ 2.2-4382. Design-build or construction management contracts for local public bodies authorized.

A. Any local public body may enter into a contract for construction on a fixed price or not-to-exceed price construction management or design-build basis, provided that the local public body (i) complies with the requirements of this article and (ii) has by ordinance or resolution implemented procedures consistent with the procedures adopted by the Secretary of Administration for utilizing construction management or design-build contracts.

B. Prior to making a determination as to the use of construction management or design-build for a specific construction project, a local public body shall have in its employ or under contract a licensed architect or engineer with professional competence appropriate to the project who shall (i) advise such public body regarding the use of construction management or design-build for that project and (ii) assist such public body with the preparation of the Request for Proposal and the evaluation of such proposals.

C. A written determination shall be made in advance by the local public body that competitive sealed bidding is not practicable or fiscally advantageous, and such writing shall document the basis for the determination to utilize construction management or design-build, including the determination of the project's complexity. The determination shall be included in the Request for Qualifications and be maintained in the procurement file.

D. Procedures adopted by a local public body for construction management pursuant to this article shall include the following requirements:

1. Construction management may be utilized on projects where the project cost is expected to be less than the project cost threshold established in the procedures adopted by the Secretary of Administration for utilizing construction management contracts, provided that (i) the project is a complex project and (ii) the project procurement method is approved by the local governing body. The written approval of the governing body shall be maintained in the procurement file;

2. Public A local public body must make the decision to use a construction management or design-build method of procurement by adopting a resolution or motion to that effect prior to issuing a Request for Qualifications. The local public body shall publish a notice on the Department's central electronic procurement website, known as eVA, or its own website, at least 14 days prior to the meeting at which such resolution or motion will be considered. The local public body shall also post a notice of the Request for Qualifications is posted on the Department's central electronic procurement website, known as eVA, or its own website at least 30 days prior to the date set for receipt of qualification proposals;

3. The construction management contract is entered into no later than the completion of the schematic phase of design, unless prohibited by authorization of funding restrictions;

4. Prior construction management or design-build experience or previous experience with the Department's Bureau of Capital Outlay Management shall not be required considered as a prerequisite or factor for award of a contract. However, in the selection of a contractor, the local public body may consider the experience of each contractor on comparable projects;

5. Construction management contracts shall require that (i) no more than 10 percent of the construction work, as measured by the cost of the work, be performed by the construction manager with its own forces and (ii) the remaining 90 percent of the construction work, as measured by the cost of the work, be performed by subcontractors of the construction manager, which the construction manager shall procure by publicly advertised, competitive sealed bidding to the maximum extent practicable. The provisions of this subdivision shall not apply to construction management contracts involving infrastructure projects;

6. The procedures allow for a two-step competitive negotiation process; and

7. Price is a critical basis for award of the contract; and

8. The procedures require the local public body to provide documentation for the processes used for the final selection to all the unsuccessful proposers, upon request.

E. Procedures adopted by a local public body for design-build construction projects shall include a two-step competitive negotiation process consistent with the standards established by the Division of Engineering and Buildings of the Department for state public bodies.

§ 2.2-4383. Reporting requirements.

A. The Department shall report by December 1 of each year to the Governor and the Chairmen of the House Committee on Appropriations, the House Committee on General Laws, the Senate Committee on Finance and Appropriations, and the Senate Committee on General Laws and Technology the following information: (i) the number of projects reviewed pursuant to Articles 2 (§ 2.2-4380) and 3 (§ 2.2-4381) and (ii) for each project (a) the identity of the state public body or covered institution and a description of each such project, (b) the estimated cost of the project at the time of the Department's review, (c) the recommendation made by the Department concerning the proposed procurement method, and (d) if such project was a construction management or design-build project, the qualifications that made such project complex, and (e) the final procurement method used by the state public body or covered institution.

B. All public bodies subject to the provisions of this chapter shall report no later than November 1 of each year to the Director of the Department on all completed capital projects in excess of $2 million, which report shall include at a minimum (i) the procurement method utilized, (ii) the project budget, (iii) the actual project cost, (iv) the expected timeline, (v) the actual completion time, and (vi) if such project was a construction management or design-build project, the qualifications that made the project complex, and (vii) any post-project issues.

The Department shall consolidate received report data and submit the consolidated data to the Governor and Chairmen of the House Committee on Appropriations and the Senate Committee on Finance and Appropriations by December 1 of each year.