SEARCH SITE

VIRGINIA LAW PORTAL

SEARCHABLE DATABASES

ACROSS SESSIONS

Developed and maintained by the Division of Legislative Automated Systems.

2020 SESSION

  • | print version

HB 443 Coal combustion residuals impoundment; closures in Giles and Russell Counties.

Introduced by: Jennifer Carroll Foy | all patrons    ...    notes | add to my profiles | history

SUMMARY AS PASSED:

Coal combustion residuals impoundment; Giles and Russell Counties; closure. Requires the owner or operator of any coal combustion residuals (CCR) unit, defined in the bill to include a coal ash pond or landfill, at the Glen Lyn Plant and the Clinch River Plant in Giles and Russell Counties, respectively, to close such CCR unit under certain circumstances by removing all of the CCR for (i) recycling, known as encapsulated beneficial use, or (ii) deposition in a permitted and lined landfill that meets certain federal standards. The measure requires that any owner or operator beneficially reuse such removed CCR if doing so is anticipated to reduce costs. Such a closure project shall be completed within 15 years of the start of excavation and shall be accompanied by an offer by the owner or operator to provide connection to a municipal water supply for every residence within one-half mile or, if such connection is not feasible, to provide water testing for any such residence.

The bill provides that if the owner or operator moves the CCR off-site, it shall develop a transportation plan in consultation with any county, city, or town in which the CCR units are located and any county, city, or town within two miles of the CCR units for any truck transportation that minimizes the effects on adjacent property owners and surrounding communities. The bill requires the owner or operator of a CCR unit to accept and review on an ongoing basis sufficiently detailed proposals to beneficially reuse any CCR that are not already subject to a removal contract. The bill requires that any entity conducting the closure (a) identify options for utilizing local workers, (b) consult with the Commonwealth's Chief Workforce Development Officer on opportunities to advance the Commonwealth's workforce goals, and (c) give priority to the hiring of local workers.

The bill requires the CCR unit owner or operator to submit two biennial reports beginning October 1, 2023, and continuing until closure of all of its CCR units is complete. One report describes closure plans, progress, a detailed accounting of the amounts of CCR that have been beneficially reused and the amount of CCR that have been landfilled, the utilization of transportation options, water monitoring results, and other aspects of the closure process; the other report contains the beneficial reuse proposals that the owner or operator has received and its analysis of such proposals.

The measure provides that all costs associated with closure of a CCR unit shall be recoverable through a rate adjustment clause authorized by the State Corporation Commission (the Commission), provided that (1) when determining the reasonableness of such costs, the Commission shall not consider closure in place of the CCR unit as an option and (2) the annual revenue requirement recoverable through a rate adjustment clause shall not exceed $40 million on a Virginia jurisdictional basis for the Commonwealth in any 12-month period, provided that any under-recovery amount of revenue requirements incurred in excess of $40 million in a given 12-month period shall be deferred and recovered through the rate adjustment clause over up to three succeeding 12-month periods. The bill provides that costs may begin accruing on July 1, 2020, but no approved rate adjustment clause charges shall be included in customer bills until July 1, 2022; any such costs shall be allocated to all customers of the utility in the Commonwealth as a non-bypassable charge, irrespective of the generation supplier of any such customer; and any such costs that are allocated to the utility's system customers outside of the Commonwealth that are not actually recovered from such customers shall be included for cost recovery from jurisdictional customers in the Commonwealth through the rate adjustment clause. The measure prohibits cost recovery for any fines or civil penalties resulting from violations of federal or state law.

SUMMARY AS PASSED HOUSE:

Coal combustion residuals impoundment; Giles and Russell Counties; closure. Requires the owner or operator of any coal combustion residuals (CCR) unit, defined in the bill to include a coal ash pond or landfill, at the Glen Lyn Plant and the Clinch River Plant in Giles and Russell Counties, respectively, to close such CCR unit by removing all of the CCR for (i) recycling, known as encapsulated beneficial use, or (ii) deposition in a permitted and lined landfill that meets certain federal standards. The measure requires that any owner or operator beneficially reuse such removed CCR if doing so is anticipated to reduce costs. Such a closure project shall be completed within 15 years of the start of excavation and shall be accompanied by an offer by the owner or operator to provide connection to a municipal water supply for every residence within one-half mile or, if such connection is not feasible, to provide water testing for any such residence.

The bill provides that if the owner or operator moves the CCR off-site, it shall develop a transportation plan in consultation with any county, city, or town in which the CCR units are located and any county, city, or town within two miles of the CCR units for any truck transportation that minimizes the effects on adjacent property owners and surrounding communities. The bill requires the owner or operator of a CCR unit to accept and review on an ongoing basis sufficiently detailed proposals to beneficially reuse any CCR that are not already subject to a removal contract. The bill requires that any entity conducting the closure or corrective action work (a) identify options for utilizing local workers, (b) consult with the Commonwealth's Chief Workforce Development Officer on opportunities to advance the Commonwealth's workforce goals, and (c) give priority to the hiring of local workers.

The bill requires the CCR unit owner or operator to submit two biennial reports beginning October 1, 2023, and continuing until closure of or corrective action at all of its CCR units is complete. One report describes closure plans, progress, a detailed accounting of the amounts of CCR that have been beneficially reused and the amount of CCR that have been landfilled, the utilization of transportation options, water monitoring results, and other aspects of the closure process; the other report contains the beneficial reuse proposals that the owner or operator has received and its analysis of such proposals.

The measure provides that all costs associated with closure of a CCR unit shall be recoverable through a rate adjustment clause authorized by the State Corporation Commission (the Commission), provided that (1) when determining the reasonableness of such costs, the Commission shall not consider closure in place of the CCR unit as an option and (2) the annual revenue requirement recoverable through a rate adjustment clause shall not exceed $40 million on a Virginia jurisdictional basis for the Commonwealth in any 12-month period, provided that any under-recovery amount of revenue requirements incurred in excess of $40 million in a given 12-month period shall be deferred and recovered through the rate adjustment clause over up to three succeeding 12-month periods. The bill provides that costs may begin accruing on July 1, 2020, but no approved rate adjustment clause charges shall be included in customer bills until July 1, 2022; any such costs shall be allocated to all customers of the utility in the Commonwealth as a non-bypassable charge, irrespective of the generation supplier of any such customer; and any such costs that are allocated to the utility's system customers outside of the Commonwealth that are not actually recovered from such customers shall be included for cost recovery from jurisdictional customers in the Commonwealth through the rate adjustment clause. The measure prohibits cost recovery for any fines or civil penalties resulting from violations of federal or state law.

SUMMARY AS INTRODUCED:

Coal combustion residuals impoundment; Giles and Russell Counties; closure. Requires the owner or operator of any coal combustion residuals (CCR) unit, defined in the bill to include a coal ash pond or landfill, in Giles or Russell County at the Glen Lyn Plant and the Clinch River Plant to close such CCR unit by removing all of the CCR for (i) recycling, known as encapsulated beneficial use, or (ii) deposition in a permitted and lined landfill that meets certain federal standards. The measure requires that any owner or operator beneficially reuse no less than 6.8 million cubic yards in aggregate of such removed CCR from no fewer than two of the sites. Such a closure project shall be completed within 15 years of its initiation and shall be accompanied by an offer by the owner or operator to provide connection to a municipal water supply for every residence within one-half mile, or if such connection is not feasible, the owner or operator shall offer to provide water testing for any such residence.

The bill provides that if the owner or operator moves the CCR off-site, it shall develop a transportation plan in consultation with any county, city, or town in which the CCR units are located and any county, city, or town within two miles of the CCR units for any truck transportation that minimizes the effects on adjacent property owners and surrounding communities. The bill requires the owner or operator of a CCR unit to accept and review on an ongoing basis sufficiently detailed proposals to beneficially reuse any CCR that are not already subject to a removal contract. The bill requires that any entity conducting the closure work (i) identify options for utilizing local workers, (ii) consult with the Commonwealth's Chief Workforce Development Officer on opportunities to advance the Commonwealth's workforce goals, and (iii) give priority to the hiring of local workers.

The bill requires the CCR unit owner or operator to submit two biennial reports beginning October 1, 2023, and continuing until closure of all of its CCR units is complete. One report describes closure plans, progress, a detailed accounting of the amounts of CCR that have been beneficially reused and the amount of CCR that have been landfilled, the utilization of transportation options, water monitoring results, and other aspects of the closure process; the other report contains the beneficial reuse proposals that the owner or operator has received and its analysis of such proposals.

The measure provides that all costs associated with closure of a CCR unit shall be recoverable through a rate adjustment clause authorized by the State Corporation Commission (the Commission) provided that (i) when determining the reasonableness of such costs the Commission shall not consider closure in place of the CCR unit as an option and (ii) the annual revenue requirement recoverable through a rate adjustment clause shall not exceed $225 million on a Virginia jurisdictional basis for the Commonwealth in any 12-month period, provided that any under-recovery amount of revenue requirements incurred in excess of $225 million in a given 12-month period shall be deferred and recovered through the rate adjustment clause over up to three succeeding 12-month periods. The bill provides that costs may begin accruing on July 1, 2020, but no approved rate adjustment clause charges shall be included in customer bills until July 1, 2022; any such costs shall be allocated to all customers of the utility in the Commonwealth as a non-bypassable charge, irrespective of the generation supplier of any such customer; and any such costs that are allocated to the utility's system customers outside of the Commonwealth that are not actually recovered from such customers shall be included for cost recovery from jurisdictional customers in the Commonwealth through the rate adjustment clause. The measure prohibits cost recovery for any fines or civil penalties resulting from violations of federal or state law.