Virginia Information Technologies Agency (136)
427. | Information Technology Planning and Quality Control (82800) | 5,745,975 | 3,448,175
| | | 5,746,285 | 3,368,279
| | | |
| | Information Technology Investment Management (Itim) Oversight Services (82801) | 1,387,408 | 1,387,408
| | | 1,387,718 | 1,307,512
| | Enterprise Development Services (82803) | 4,358,567 | 2,060,767
| | Procurement and Contracting Services (82804) | sum suf | sum suf
| | Web Development and Support Services (82805) | sum suf | sum suf
| | | |
| Fund Sources: | General | 2,016,673 | 2,016,673
| | | 2,016,983 | 1,936,777
| | Dedicated Special Revenue | 1,153,400 | 1,355,600
| | Federal Trust | 2,575,902 | 75,902
|
Authority: Title 2.2, Chapter 20.1, Code of Virginia.
A.1. Notwithstanding any other provision of law except the
limitations imposed by § 2.2-518, § 2.2-4803 and § 2.2-4806, Code of Virginia, Executive
Department agencies and institutions may enter into management agreements with
CGI Technologies & Solutions, Inc. (CGI) for debt collection and cost
recovery services pursuant to Statements of Work 6 and 7 of the Enterprise
Applications Master Services Agreement between the Commonwealth of Virginia and
CGI. Executive Department agencies and institutions may also enter into
additional Statements of Work with CGI pursuant to § 2.2.4 of the Enterprise
Applications Master Services Agreement for services related to such Agreement,
which may include, but not be limited to, services supporting projects in the
five towers of enterprise-level endeavors (financial management, human resource
management, supply chain management, administrative management, and applications
development and management). Work on enhanced collections and recoveries
or any additional Statements of Work pursuant to § 2.2.4 of the Enterprise
Applications Master Services Agreement shall not proceed if they commit the
Commonwealth to expanding or significantly altering any existing federal or
state program without the review and approval of the Governor and prior
consultation with the Chairmen of the House Appropriations and Senate Finance
Committees.
2. Moneys resulting from enhanced collections and cost recoveries
pursuant to this Item shall be held in the Virginia Technology Infrastructure
Fund as established by § 2.2-2023, Code of Virginia.
3. The Auditor of Public Accounts shall provide the Governor and
the Chairmen of the House Appropriations and Senate Finance Committees no later
than December 1, 2013, a report of the result of a financial and operational
audit of CGI and its subcontractors, as provided in parts 15.2 and 15.3 of the
Enterprise Applications Master Services Agreement. The audit shall review all
management agreements between CGI and Executive Department agencies and
institutions pursuant to Statements of Work 6 and 7 and include a review of CGI
and its subcontractors' performance with regard to measured service levels.
B.1. As established in § 3-2.03 of this act, working capital
advances totaling up to $90,000,000 will provide for the development of
enterprise applications for the Commonwealth, including the development of the
performance budgeting and financial management systems. These working
capital advances will be repaid from anticipated revenues from enhanced
collections, cost recoveries, inter-agency collaborative projects and other
initiatives to be collected pursuant to this item and will be deposited into
the Virginia Technology Infrastructure Fund. No funds derived from these
working capital advances shall be expended without the prior budget approval of
the Secretaries of Technology and Finance. The State Comptroller shall
notify the Governor and the Chairmen of the House Appropriations and Senate
Finance Committees prior to any approved expenditure.
2. Funds received from the working capital advance will be used
only for enterprise resource planning and development costs. No funds received
from this working capital advance shall be used as payment toward operating
costs of this or any other program.
3. At the end of each fiscal year, the Governor is authorized
to apply up to $2,000,000 from the unappropriated general fund balance in this
act to pay down this working capital advance in the event other repayment
sources in this act are not available or are insufficient to maintain a
reasonable schedule for the payback of the working capital advance.
C.1. In order to minimize the cost of information systems
development, the Secretary of Technology shall work with all Cabinet
Secretaries and their agencies to develop Commonwealth data standards for
citizen-centric data, personnel, recipient information, and other common
sources of information gathered by the Commonwealth and in use by systems set
out within this item. Not later than November 1, 2012, the Secretary of
Technology shall communicate an initial plan that will provide at least an
estimated timetable, cost and description of the anticipated scope of the
effort to the Governor and the Chairmen of the House Committee on
Appropriations and the Senate Committee on Finance. A final plan, with a
specified timetable and costs required to gather, approve and publish these
standards, shall be communicated to the Governor and the Chairmen of the House
Committee on Appropriations and the Senate Committee on Finance by July 1,
2013. In developing the plan, the Secretary of Technology shall use best
practices, federal requirements, and existing data standards.
2. Where active projects in this item, have implemented
standardized data, the Secretary of Technology shall work with all Cabinet
Secretaries and their agencies to determine if these standards should be
adopted as Commonwealth data standards for use in active or future major IT
projects or investments. Where active projects in this item do not conform
to the Commonwealth’s data standard, the Secretary of Technology shall include
in the interim a plan for how the Secretary of Technology will identify data
standards that should be adopted as Commonwealth data standards and the
estimated cost of ensuring that each active IT project in the item complies
with the Commonwealth data standard.
D.1. Notwithstanding the provisions of §§ 2.2-1509, 2.2-2007 and
2.2-2017, Code of Virginia, the scope of formal reporting on major information technology
projects in the Recommended Technology Investment Projects (RTIP) report
is reduced beginning in the second year. The efforts involved in
researching, analyzing, reviewing, and preparing the report will be streamlined
and project ranking will be discontinued. Project analysis will be
targeted as determined by the Chief Information Officer (CIO) and the Secretary
of Technology. Information on major information technology investments
will continue to be provided General Assembly members and staff.
Specifically, the following tasks will not be required, though the task may be
performed in a more streamlined fashion: (i) The annual report to the
Governor, the Secretary, and the Joint Commission on Technology and
Science; (ii) The annual report from the CIO for submission to the
Secretary, the Information Technology Advisory Council, and the Joint
Commission on Technology and Science on a prioritized list of Recommended
Technology Investment Projects (RTIP Report); (iii) The development
by the CIO and regular update of a methodology for prioritizing projects based
upon the allocation of points to defined criteria and the inclusion of this
information in the RTIP Report; (iv) The indication by the CIO of the
number of points and how they were awarded for each project recommended for
funding in the RTIP Report; (vi) The reporting, for each project listed
in the RTIP, of all projected costs of ongoing operations and maintenance
activities of the project for the next three biennia following project
implementation, a justification and description for each project baseline
change, and whether the project fails to incorporate existing standards for the
maintenance, exchange, and security of data; and (vii) The
reporting of trends in current projected information technology spending by
state agencies and secretariats, including spending on projects, operations and
maintenance, and payments to Virginia Information Technologies Agency.
2. Pursuant to §2.2-1509.3, Code of Virginia, the following
major information technology projects are active and have been approved and
recommended for funding by the Secretary of Technology. The data listed was
self-reported to the Virginia Information Technologies Agency by the
responsible agencies. These projects are supported by strong business cases and
thus were considered as priorities for funding in this biennium.
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Social Services (765) -- Automated Child
Care Subsidy System
|
Jan 11, 2010
|
Not Available
|
$20,364,802
|
|
|
Completed
|
|
Implement a Child Care Subsidy Payment System (CCSPS) for
Child Care Subsidies. The CCSPS will allow for real-time documentation
of attendance and enable the program to better address issues relating to
improper use of subsidies.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Social Services (765) – EDSP –
Eligibility Modernization – MAGI Project
|
Oct 22, 2012
|
Oct 31, 2013
|
$22,525,210
|
The Eligibility Modernization Modified Adjusted Gross
Income (MAGI) project will implement a single Medicaid case management system
for MAGI Medicaid and CHIP/FAMIS categories by modifying Virginia Case
Management System (VaCMS) for new applications. This initiative will
implement a streamlined, secure, and interactive customer experience that
will maximize automation and real-time adjudication while protecting privacy
and personally identifiable information. This enhancement to the Customer
Portal will determine MAGI Medicaid eligibility on-line, perform MMIS
enrollment, perform MMIS disenrollment, access Federal and State verification
systems through Exchanges, and leverage web-services such as the Commonwealth
Authentication Service (CAS) and the Enterprise Data Management (EDM)
solution projects under eHHR.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$2,305,736
|
$768,579
|
Nongeneral Fund
|
$14,588,173
|
$4,862,724
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Social Services (765) – EDSP –
Eligibility Modernization – Program Migration Project
|
Oct 22, 2012
|
Mar 31, 2016
|
$75,212,015
|
The modernization and migration consists of MAPPER UNISYS
system replacement for the ADAPT application and the Energy Assistance
Program application. ADAPT is the current eligibility determination and
case management system for SNAP, TANF, Employment Service. The
Eligibility Modernization Program Migration Project will convert the cases
that contain the programs in ADAPT and the Energy system into VaCMS along
with accepting new applications for these programs via online (Customer
Portal) and paper (manual data entry) processes. This project also
involves the external rules engine (iLOG). All program rules will be
incorporated into iLOG with the outcome of eligibility determination,
authorization, and case management within this single case management solution.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$2,924,187
|
$5,848,374
|
Nongeneral Fund
|
$8,646,892
|
$17,293,784
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Social Services (765) – EDSP –
Eligibility Modernization – Conversion
|
Nov 13, 2012
|
Apr 30, 2015
|
$10,583,249
|
The EDSP Eligibility Modernization Conversion project will
focus its efforts on converting the data in the ADAPT legacy system and DMAS
CHAMPS legacy system for the Families & Children’s Medicaid, CHIP, and
FAMIS categories into VaCMS. The CMS federal requirement stipulates for
these eligible ongoing Medicaid categories (staring April 2014) at the time
of their renewal process, continued eligibility must be evaluated against the
new MAGI Medicaid rules. This conversion project will move those
existing cases into VaCMS and eligibility determination be performed by the
external rules engine accomplished in the Eligibility Modernization MAGI
project. Conversion will be performed on a month by month schedule
(based on the Medicaid renewal date) until all cases for these categories
have been converted from these two legacy systems.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$297,654
|
$892,962
|
Nongeneral Fund
|
$2,348,158
|
$7,044,475
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Accounts (151) -- Cardinal Project
|
Apr 17, 2008
|
Oct 2014
|
$114,329,233
|
|
|
Completed
|
$58,337,353
|
The Department of Accounts is replacing its statewide general
ledger system- CARS. The new system will serve as the
Commonwealth’s general ledger system of record. The functional scope of
the project includes General Ledger, Cash Receipting, and Cash Disbursement,
which is considered the Enterprise Base System. This project consists
of roll-out of the base application to replace the Virginia Department of
Transportation’s (VDOT) FMS II system, roll-out of the Enterprise Base System
at the Department of Accounts Fiscal Office, and statewide roll-out to all
agencies of the Enterprise Base System, replacing CARS as the Commonwealth’s
general ledger system. Estimated project cost includes VDOT costs.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$22,333,480
|
$29,903,680
|
|
$164,978
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Professional and Occupational Regulation
(222) -- EAGLES
|
Mar 1, 2007
|
Not Available
|
$1,499,000
|
|
|
Jan 31, 2014
|
$7,977,793
|
EAGLES will be a web-enabled application implemented to
replace two legacy systems, CLES and ETS. EAGLES will also support the
agency's new business requirements. This project is in line with the
Commonwealth’s electronic government initiative, which requires that the
Department be aligned closely with the Digital Signatures and COVA PIN
initiative. Project Scope: This project scope includes the
development of the EAGLES web-enabled application to replace the legacy systems,
CLES and ETS, and the expansion of the system to include the Department’s new
business requirements.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$1,260,600
|
$376,500
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Social Services (765) -- EDS - Customer
Portal Enterprise Delivery System Program
|
Feb 8, 2011
|
Sep 14, 2012
|
$9,722,312
|
|
|
|
$11,201,779
|
The Enterprise Delivery System Program represents four major
projects: the EDSP Worker Portal, the EDSP Customer Portal, the EDSP Master
Customer ID and the EDSP Document Management Imaging System. The four
major projects are the foundation for implementing the VDSS vision of a
self-service model that is efficient, effective and provides a streamlined
customer friendly experience. Within the vision, clients will be able
to file applications for benefits or services through an online application
process, report changes, and manage benefit “accounts” online.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$31,499
|
$0
|
Nongeneral Fund
|
$65,501
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Department of Transportation (501) -- Highway
Performance Monitoring System (HPMS)
|
Sep 1, 2009
|
Not Available
|
$1,000,000
|
|
|
Completed
|
$1,316,375
|
The Highway Performance Monitoring System (HPMS) supports the
Roadway Network Systems (RNS) program within the Department of Transportation
(VDOT). The HPMS project includes adding new data fields to RNS for new
data; adding classified public roads to the Highway Traffic Records
Information System (HTRIS); building a user interface to add/edit data in
RNS; and developing a means of managing and creating a file to send all
required data to the Federal Highway Administration (FHWA).
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$0
|
|
$35,000
|
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Department of Transportation (501) – CSC
System 2.0
|
Aug 6, 2012
|
Jun 30, 2014
|
$4,500,000
|
The Customer Service Center Portal 2.0 project will
enhance the functionality and usability of the Customer Service Center
Portal, and will: Enable Customer Service Center Agents to better
respond to customer inquiries; – Promote VDOT’s ability to share information
throughout the agency; and Enhance VDOT’s ability to quickly and efficiently
respond to citizen requests for roadway service/ maintenance.
|
|
|
|
|
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$2,754,340
|
$0
|
|
|
$3,053,060
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Department of Transportation (501) –
Construction Documentation Management
|
Aug 31, 2012
|
Jun 28, 2013
|
$1,100,000
|
This project is to implement a consistent way of managing construction
documents, and in particular electronic documents, across all districts.
Part of this initiative is to also to automate the Advertisement and
Award process workflow to optimize its document management during the initial
stages of the construction management lifecycle.
|
|
|
|
|
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$1,100,000
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Department of Transportation (501) – Snow
Plowing Tracking
|
Oct 12, 2012
|
May 31, 2014
|
$5,220,380
|
The scope of the Snow Plow Tracking Project is to provide a
comprehensive approach for VDOT to manage its snow plowing tracking
initiative across the entire Commonwealth. VDOT intends to provide snow
plowing tracking and display for operational use and public consumption
statewide on all VDOT managed roadways at the street level. The Department
also wishes to improve customer services and transparency of services being
provided across the Commonwealth and improve internal business operations
across the enterprise.
|
|
|
|
|
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$2,805,760
|
$2,414,620
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Medical Assistance Services (602) -- HIPAA
Upgraded Transactions (5010/NCPDPD.0)
|
Apr 19, 2011
|
Feb 29, 2012
|
$8,624,000
|
|
|
Completed
|
$1,446,945
|
The Centers for Medicare and Medicaid Services (CMS) has proposed
regulations requiring that all X12 Transactions be upgraded to the 5010
versions and that the ICD-10 version of the code sets be implemented.
DMAS must implement the new versions in order to remain HIPAA compliant and
continue to receive and send electronic eligibility, claims, and payment data
with approximately 50,000 providers and 300 plus service centers.
Implementation of the changes will require modification to the MMIS and
extensive provider outreach and trading partner testing.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
|
$212,525
|
|
Nongeneral Fund
|
$0
|
$0
|
|
$1,234,420
|
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Medical Assistance Services (602) – ACA –
NCCI (National Correct Coding Initiative)
|
Sep 28, 2012
|
Jul 31, 2013
|
$1,539,247
|
In accordance with the implementation of the Patient Protection
and Affordable Care Act of 2010 and as amended by the Health Care and
Education Recovery Act of 2010 (known together as the Affordable Care Act),
the Virginia Department of Medical Assistance Services is conducting a
project to comply with the Mandatory State Use of National Correct Coding
Initiative (NCCI).
|
|
|
|
|
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$160,111
|
$0
|
Nongeneral Fund
|
$1,379,136
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia State Police (156) -- Law Enforcement Activity
Management System
|
Jun 13, 2007
|
Not Available
|
$3,530,000
|
|
|
Feb 15, 2013
|
$3,421,600
|
The LEAMS project will provide a comprehensive system to
support the documentation of criminal investigations and related law
enforcement activities and reduce the agency’s dependence on burdensome
paper-based workflows and difficult-to-change legacy technologies. The
system will make use of up-to-date technology to upgrade process controls,
management/supervisory oversight, data quality, processing timeliness, system
access, analytical tools, and intra-agency and inter-agency cooperation
needed to maintain quality law enforcement records as mandated under §
15.2.-1722 of the Code of Virginia.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$13,200
|
$0
|
Nongeneral Fund
|
$712,000
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia State Police (156) – AFIS Upgrade to Integra –
Phase 1
|
Jan 18, 2012
|
Nov 18, 2012
|
$1,010,354
|
Upgrade the current AFIS system hardware and software with
a new NEC Integra ID system. This new system will be installed at the
VSP central site and will offer added flexibility in the automated workflow
options and specifications. The proposed redundant hardware solution
will offer improved Disaster Recovery possibilities. The proprietary
hardware matchers will be replaced with off-the-shelf hardware and software
matching. Phase 1: Phase 1 of the project will include the new
functionality for Mobile ID identifications and responses and submission of
the searches to the FBI Repository of Individuals of Special Concern (RISC).
This will require the current database to be converted to the new
Automated Biometric Identification System (ABIS) format. New hardware
is needed to support the new functionality and the new database.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Behavioral Health and Developmental Services
(720) -- Medication Management System: Pharmacy Systems Software
Application
|
Oct 6, 2008
|
Not Available
|
$3,500,000
|
|
|
Completed
|
|
The Medication Management System will replace the legacy
pharmacy system with an integrated medication management application sharing
an electronic medical record repository. The scope of the project
is to implement a medication management system that utilizes an electronic
medical record repository at each DBHDS facility. The project would
replace legacy systems and integrate with recent IT investments such as
AVATAR for patient/resident admissions, discharges, and reimbursements.
The project would also replace the outdated In-Patient and Aftercare pharmacy
systems.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Planning and Budget (122) -- Performance
Budgeting Solution
|
Jul 24, 2009
|
Jan 20, 2012
|
$11,402,864
|
|
|
Completed
|
$15,000,312
|
The project is the implementation of a performance budgeting
system to replace the current budgeting and strategic planning applications
(PROBUD, WebBEARS, Budgetwise and Expendwise). Today the Commonwealth’s
strategic planning and budget development processes use a wide range of
disparate systems. These systems have limited integration and
interfacing capabilities. The Commonwealth currently relies on numerous
systems, applications, and processes to support the Performance Budgeting
business process.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$0
|
|
$1,842,283
|
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Corrections (799) -- Phase 2 and 3 Virginia
Correctional Information System (CORIS)
|
Jun 22, 2006
|
Not Available
|
$17,781,554
|
|
|
Nov 30, 2012
|
$23,093,458
|
The Department of Corrections (DOC) has established an automated
Offender Management Information System (OMS) Program, now called
VirginiaCORIS. This is a major technology effort and is critical to the
successful accomplishment of the DOC mission. The VirginiaCORIS Program
will be composed of multiple major projects, and will result in a single,
fully integrated system that should replace most of the DOC’s current
offender-related application portfolio. The selected solution is
already in production in other state DOCs, with some additional required functionality
being developed and planned for deployment in the next 12 months.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
|
$1,176,100
|
|
Nongeneral Fund
|
$0
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Department of Transportation (501) -- Roadway
Inventory Management System
|
Jan 1, 2010
|
Not Available
|
$3,005,115
|
|
|
Aug 30, 2013
|
$4,995,000
|
The Roadway Inventory Management System (RIMS) supports the
Roadway Network Systems (RNS) program within the Department of Transportation
(VDOT). RIMS involve a process redesign that will assist RNS in providing
road inventory and attribute data on Straight Line Diagrams (SLDs) and
maps. The current process and systems for capturing roadway inventory
data are slow, inefficient and do not portray an accurate picture of the
ground truth. No mapping capability is present today. Upon
completion, RIMS will support RNS in providing streamlined business
processes; timely updates to inventory; advanced inventory query and
reporting; enhanced mapping functions; improved performance; and eliminate
duplicate data entry for road inventory within the Database for Administering
Changes in VDOT Highway Systems (DACHS) application.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Education (201) -- State Longitudinal Data
System (SLDS)
|
Feb 16, 2011
|
Aug 30, 2013
|
$13,522,897
|
|
|
Sep 30, 2013
|
|
The Virginia Department of Education (VDOE) —in partnership
with the Office of the Governor, the State Council of Higher Education
(SCHEV), the Virginia Community College System, the Virginia Information
Technologies Agency, and Virginia’s workforce agencies—proposes to expand on
the advancements we have made through our current Statewide Longitudinal Data
Systems (SLDS) grant.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$3,002,565
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Employment Commission (182) -- Unemployment
Insurance Modernization
|
Sep 17, 2009
|
Sep 27, 2013
|
$58,831,331
|
|
|
Sep 11, 2014
|
$58,540,155
|
The VEC needs to modernize the Unemployment Insurance
Benefits and Tax (UIBT) system. The current system is based on VEC
priorities identified in the mid-1980s. Since that time, the statutory environment
and the business processes have changed. The current UIBT system is
difficult to upgrade and costly to maintain when compared to systems that are
available in today’s market. As a result of these concerns, VEC has
identified two goals for the Unemployment Insurance Modernization Project:
·Replace the existing UIBT applications using a foundation of new technology
and improved design methods to improve flexibility and maintainability.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$14,594,530
|
$8,052,200
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Department of Transportation (501) -- VGIN/VDOT Road
Centerline Transition Project
|
Jun 15, 2010
|
Not Available
|
$1,053,521
|
|
|
Completed
|
|
The Commonwealth of Virginia has established the goal that
for each type of data there will be a single source system of record. In
addition, the Commonwealth Chief Information Officer (CIO) has mandated that
the Roadway Network System (RNS) migrate to and use the enterprise road
centerlines (E-RCL) maintained by the Virginia Geographic Information Network
(VGIN). This project supports achievement of both goals by addressing
two main business problems: 1) the existence of multiple sources of
road centerline (RCL) data, and 2) the duplication of effort required to
maintain these multiple data sets.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Health (601) -- Women, Infants, Children (WIC)
Electronic Benefits Transfer (EBT) Project
|
Jan 8, 2009
|
Oct 31, 2012
|
$3,980,666
|
|
|
Aug 26, 2013
|
$6,619,018
|
The Women, Infants, and Children (WIC) Electronic Benefits Transfer
(EBT) Project will develop and implement the business processes and
associated technology to provide electronic WIC (e-WIC) issuance, redemption,
payment, and reconciliation services to distribute food benefits in the
Virginia WIC Program. The manual, paper-based system introduces
numerous inefficiencies into the process. The project will require
procurement of a number of services including support for the development of
an Implementation Advanced Planning Document (IAPD), as required by the United
States Department of Agriculture Food and Nutrition Service, Quality
Assurance and Monitoring, and Design, Development, and Implementation of the
selected e-WIC solution. The project will implement an online,
outsourced EBT technology.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$802,075
|
$21,713
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Information Technologies Agency (136) --
Commonwealth Enterprise Data Management (EDM)
|
Sep 1, 2011
|
Aug 17, 2012
|
$7,889,520
|
|
|
Jun 21, 2013
|
$7,625,177
|
The Health and Human Resources (HHR) Secretary and the Commonwealth’s
MITA Program Manager have requested that the Virginia Information
Technologies Agency (VITA) provide an enterprise data management solution
that will store enterprise data and facilitate data sharing at an enterprise
level. The Secretary, in collaboration with the Secretary of Technology, is
leading the Commonwealth's efforts to improve and modernize the Medicaid
program’s information technology infrastructure.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
|
$64,132
|
|
Nongeneral Fund
|
$2,080,000
|
$0
|
|
$577,000
|
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Information Technologies Agency (136) -- Commonwealth
Service Oriented Architecture
|
Sep 21, 2011
|
Aug 17, 2012
|
$8,347,520
|
|
|
Nov 29, 2013
|
$11,756,392
|
This program created the Commonwealth Service Oriented
Architecture Project to provide the necessary infrastructure and governance. As
such, the project shall procure, install, and configure the software and
hardware necessary to establish test, production, and disaster recovery
environments. In addition, the project shall institute an appropriate Center
of Competence and related governance. Finally, in concert with the
Commonwealth Enterprise Data Management (EDM) Project, this project shall
develop and deploy the web services for the Commonwealth’s EDM solution.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
|
$68,080
|
|
Nongeneral Fund
|
$2,416,000
|
$0
|
|
$612,724
|
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Information Technologies Agency (136) – Telecommunications
Expense (Management) and Billing Systems (TEBS)
|
May 1, 2013
|
Mar 31, 2015
|
$3,000,000
|
The Telecommunications Expense (Management) and Billing
System (TEBS) project will procure and implement a modern, integrated, user-friendly
telecommunications expense management and billing solution. The TEBS project
is for the Virginia Information Technologies Agency (VITA). The goal of
the TEBS project is to replace the 30+ year-old mainframe Telecommunications
Inventory Billing System (TIBS) that currently supports VITA’s
Telecommunications Service Delivery with a modern integrated, user-friendly
system that supports all of the existing TIBS functionality and providing
additional telecommunication expense functionality.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$1,820,000
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Department of Transportation (501) -- Urban Roads
Consolidation Conversion Project
|
Oct 11, 2010
|
Dec 12, 2013
|
$2,722,535
|
VDOT is required to submit annual reports to the Federal Highway
Administration as part of the Highway Performance Monitoring System
(HPMS). To expedite the generation of these reports, VDOT desires to
generate a Linear Referencing System based on both local government roadway
information and Virginia Geographic Information Network (VGIN) urban data
set. This project will consolidate the local data, the VGIN data and
VDOT's data into a single set.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$1,142,785
|
$329,300
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Health (601) -- Electronic Death
Registration (EDR)
|
Mar 22, 2011
|
Dec 30, 2014
|
$3,003,500
|
The Electronic Death Registration (EDR) system is a proposed
web-based system that would allow for the electronic capture of death data
from funeral service licensees, state medical examiners and state
physicians. The system would allow the VDH Division of Vital Records
(DVR) and local health departments to issue and retain death certificates
electronically as opposed to the manual process that is currently used.
The Electronic Death Registration system is expected to reduce reporting
delays, improve data quality, and increase the utility of death data.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$880,500
|
$421,666
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Employment Commission (182) -- Financial
Management System
|
Aug 18, 2011
|
Mar 29, 2013
|
$4,734,900
|
|
|
Dec 31, 2013
|
$4,948,456
|
The Financial Management Accounting System will replace the current
mainframe batch system. The new system will include modules for
accounts payable, accounts receivable, general ledger, cost allocation, time
distribution and procurement. Financial data will be processed in an on-line,
real-time environment. These features will greatly improve efficiency
in financial processes, availability of management information, and the
accuracy of accounting reports, thus reducing the potential for audit
findings.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$2,018,925
|
$0
|
|
$2,495,500
|
$1,855,196
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Motor Vehicles (154) -- DMV CSI Systems
Redesign - Development and Implementation
|
Nov 15, 2010
|
Sep 1, 2013
|
$69,954,521
|
|
|
Cancelled
|
|
The CSS Redesign focuses on the fragmented processing of
DMV's three major business areas: driver, vehicle, and motor
carrier. The purpose of the redesign is to transform these fragmented
fifteen year old systems into one modernized system that is responsive to the
ever-changing needs relating to internal security, homeland security, legislative
mandates, and customer relationship management. DMV has a unique
opportunity to revolutionize the agency’s approach to fulfilling its mission,
carrying out core functions, and delivering service. DMV intends to
fully integrate processing while incorporating and leveraging the full
functionality and benefits of proposed technology solutions as well as the
technology already in place.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$22,663,410
|
$2,658,663
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Motor Vehicles (154) -- DMV FACE – DMV
Correspondence Transformation
|
Aug 15, 2012
|
Jun 30, 2013
|
$1,382,400
|
DMV issues an average of 30,000 pieces of correspondence
weekly (1.56 million annually), many of which are required by Virginia Code.
The current solution for developing and modifying correspondence has
reached its end of life and is no longer supported. It requires
professional IT resources for every change. This FACE sub-project will
replace all existing correspondence and transform the business logic which
drives it. The resulting solution will allow business owners to self-service
correspondence and play an expanded role in the creation of new artifacts.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$1,382,400
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Secretary of Health and Human Resources (188) -- Birth
Reporting Interface (BRI)
|
Dec 30, 2011
|
Dec 31, 2012
|
$2,639,952
|
|
|
Sep 30, 2014
|
$2,112,000
|
This project will establish a birth reporting service/interface
between the birth registry and the ESB. The system of record for all
birth records will be VVESTS (Virginia Vital Events and Screening Tracking
System). The proposed functionality must support a HITSAC approved data
standard which should align with the EDM standards. The project
requires use of HITSAC endorsed messaging standards.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$105,598
|
$0
|
|
$71,280
|
$142,560
|
Nongeneral Fund
|
$950,383
|
$0
|
|
$562,320
|
$1,124,640
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Motor Vehicles (154) -- Commonwealth
Authentication Services
|
Dec 18, 2011
|
Feb 29, 2012
|
$10,000,000
|
|
|
Jun 24, 2013
|
$4,408,762
|
Through the collaboration of the Technology, Health and Human
Resources, and Transportation secretariats, on-line identity authentication
services will be built for all Commonwealth agencies to use. The Commonwealth
Authentication Services (CAS) project will implement a COTS project with the
assistance of an implementation partner so that DMV, DSS, DMAS and the Health
Information Exchange (HIE) can all leverage a common authentication system
for users to gain access to selected customer-facing systems. The CAS
system will be hosted, operated and maintained by VITA as a shared service,
and participating agencies will pay to use CAS. Once CAS is fully
operational, additional agencies will be encouraged to convert over from
their own point-solutions to CAS.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
|
$389,876
|
|
Nongeneral Fund
|
$0
|
$0
|
|
$3,508,886
|
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Motor Vehicles (154) – FACE – Motor
Carrier Portal Phase 1
|
Dec 15, 2013
|
Dec 31, 2013
|
$1,797,120
|
DMV has a highly sophisticated Motor Carrier operation that
manages every aspect of driver and vehicle licensing, fuels tax, inter- and
intra-state regulations and licensing. The Motor Carrier work centers operate
in a mixed application environment with outdated systems. DMV’s commercial
carrier customers also interface with DMV through up to three different
systems depending upon the transaction. Each of the systems is at
end-of-life. Among the key business strategies for the agency, is the
recruitment of additional Motor Carrier customers. DMV has attracted
several Top 100 carriers to Virginia in the past year representing millions
in revenue and is need of system updates to remain competitive. Thus,
the need to develop a single-point of entry for all Motor Carrier customers’
needs.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$898,560
|
$898,560
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Secretary of Health and Human Resources (188) -- Death
Reporting Interface (DRI)
|
Dec 30, 2011
|
Dec 31, 2012
|
$2,639,952
|
|
|
Sep 30, 2014
|
$2,112,000
|
This project is designed to establish a death reporting
service/interfaces between the death registry and the ESB. The service
will be supported by an extract of the minimum required fields to identify a
death record. Additional development may be required to add a match
code (Yes/No) and an MPI placeholder.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$105,598
|
$0
|
|
$71,280
|
$142,560
|
Nongeneral Fund
|
$950,383
|
$0
|
|
$562,320
|
$1,124,640
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Secretary of Health and Human Resources (188) –
HIT/MITA Program
|
Nov 14, 2011
|
Apr 29, 2014
|
$53,373,320
|
The purpose of the HIT/MITA Program is to align the Commonwealth
with Federal direction relative to the American Recovery and Reinvestment Act
(ARRA) and the Patient Protection and Affordable Care Act of 2010 (PPACA).
These acts present significant funding opportunities to improve the quality
and value of American healthcare. PPACA mandates Medicaid expansion in 2014,
which is predicted to increase Virginia’s Medicaid membership by 35-45%.
Leveraging the Federal funding opportunities to offset the impact of
expansion is an important investment in Virginia’s future. The Federal
funding available under ARRA and PPACA provide opportunities to achieve the
following outcomes for Virginia; Build on current health reform efforts;
Modernize information technology infrastructure as an enabler for future
business transformation; Provide a technical environment where
standards-based interoperability is possible between new and legacy systems;
Provide web based self-directed service options for human services; Reduce
the need for large administrative and operational staff for Federal and State
programs; Reduce overall long-term technology costs for Federal and State
programs; and Provide an enterprise technology environment that is accessible
on a pay-for-use basis by Federal, State, and local governments as well as
non-government organizations, community based-services, and commercial
interests as allowed by policy.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$704,245
|
$603,304
|
Nongeneral Fund
|
$3,387,170
|
$2,848,475
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Medical Assistance Services (602) -- DMAS
Eligibility System Support
|
Jul 30, 2012
|
Jun 30, 2014
|
$4,871,340
|
|
|
Cancelled
|
|
The Patient Protection and Affordable Care Act (ACA) require
a Medicaid population expansion that will occur in 2014. Along with the
expansion a Health Insurance Exchange and a standardization of enrollment
forms across all health & human services programs will also take
place. The DMAS Eligibility System Support project will provide the
needed support to the contractor for the replacement of the eligibility
systems.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$443,292
|
$189,9820
|
Nongeneral Fund
|
$2,966,646
|
$1,271,420
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Behavioral Health and Developmental Services
(720) -- Electronic Health Records (EHR)
|
Dec 30, 2011
|
Sep 30, 2014
|
$16,000,000
|
|
|
Jun 30, 2015
|
$34,256,000
|
The Clinical Apps/EHR project will replace legacy systems
with integrated clinical applications sharing an electronic medical record repository.
The scope of the project is to implement an electronic medical record
repository and clinical applications at each DBHDS facility and Central
Office. The project would replace legacy systems and integrate with
recent IT investments such as AVATAR for patient/resident admissions,
discharges, and reimbursements.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
|
$4,380,000
|
$1,900,000
|
Nongeneral Fund
|
$2,909,418
|
$4,272,289
|
|
$12,000,000
|
$8,500,000
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Secretary of Health and Human Resources (188) --
Electronic Lab Reporting Interface (ELRI)
|
Dec 30, 2011
|
Dec 2, 2012
|
$2,074,248
|
Clinical laboratories throughout Virginia (including DGS
Department of Consolidated Laboratory Services (DCLS) and national clinical
reference laboratories submit reportable disease findings to VDH. Test orders
are submitted to DCLS and DCLS returns test results. Current partners include
VDH and a growing number of Virginia hospitals. Additional legacy
formatted exchanges between DCLS and VDH will continue until they are
converted to HL7, but the legacy messages will not be managed through the
interface. This project interfaces DCLS interfaces to the
Commonwealth's Enterprise Service Bus (ESB) for access by the Health
Information Exchange.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$107,861
|
$0
|
Nongeneral Fund
|
$721,838
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Accounts (151) -- Financial Management
Enterprise Rollout (Cardinal Project Part 3)
|
Jul 1, 2012
|
Jul 1, 2014
|
$56,991,880
|
|
|
Mar 1, 2015
|
|
This project will replace the Commonwealth's (Department of
Accounts) current financial system, Commonwealth Accounting and Reporting
System (CARS). It will be an Enterprise Resource Planning (ERP)
implementation of General Ledger and Accounts Payable, the two accounting
features currently contained within CARS. The system will be deployed
to all current day CARS users and interfaced with the financial systems that
currently interface to CARS. The scope of this project also includes
the Change Leadership and Training required to migrate off of CARS.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$22,333,480
|
$29,903,680
|
Nongeneral Fund
|
$0
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Department of Taxation Transportation
(501) -- FMS Sun Set and Data Marts
|
Sep 1, 2011
|
Dec 31, 2012
|
$2,180,000
|
|
|
Mar 15, 2013
|
$1,820,000
|
The implementation of the Cardinal Project will necessitate
the sun setting of both the FMSI and FMSII Financial Systems and retention of
business critical data. Sun Setting of these systems in an organized
fashion will create greatly reduced operational expenses from VITA. The
FMS Data Marts will retain critical data from the FMSI and FMSII Financial
Systems and create a Financial Data Store for reporting purposes. The
objective of this project is to have the data store information available to
VDOT internal systems to merge with Cardinal financial data for business
intelligence reporting.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$780,000
|
$0
|
|
$1,005,000
|
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Medical Assistance Services (602) -- HIPAA
Upgrade Code Set (ICD010)
|
Dec 15, 2011
|
Nov 29, 2013
|
$2,200,000
|
|
|
Feb 14, 2014
|
$9,872,529
|
The Centers for Medicare and Medicaid Services (CMS) has
proposed regulations requiring that all X12 Transactions be upgraded to the
5010 versions and that the ICD010 version of the code sets be
implemented. DMAS must implement the new versions in order to remain
HIPAA compliant and continue to receive and send electronic eligibility,
claims, and payment data with approximately 50,000 providers and 300 plus
service centers. Implementation of the changes will require
modification to the MMIS and extensive provider outreach and trading partner
testing.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$60,000
|
$0
|
|
$1,051,700
|
$141,441
|
Nongeneral Fund
|
$180,000
|
$0
|
|
$6,217,280
|
$1,003,907
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Motor Vehicles (154) -- KATS II: Next
Generation Knowledge Automated Testing System
|
Jun 15, 2012
|
Aug 30, 2013
|
$5,000,000
|
|
|
Dec 1, 2013
|
$1,944,693
|
The Virginia Department of Motor Vehicles seeks to acquire a
turn-key contract, through competitive negotiation, for the acquisition,
design, custom development, installation, training, and maintenance of a
network of Knowledge Automated Testing Systems (KATS) on a firm fixed price
basis. The KATS system will be installed in all DMV Customer Service Center
locations and mobile Customer Service Centers throughout the Commonwealth as
specified by DMV. This project will replace the current KATS system
with one incorporating necessary advancements in testing and technology which
were not available when the current KATS was implemented in 1993 and updated
in 2005.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$0
|
|
$1,868,298
|
$76,395
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Secretary of Health and Human Resources (188) --
Immunization Registry Interface (IRI)
|
Dec 30, 2011
|
Dec 2, 2012
|
$2,262,816
|
|
|
Sep 30, 2014
|
$1,808,000
|
Participating organizations such as hospital providers create
a file to include new and updated immunization activity for import into
Virginia Immunization Information System (VIIS) and receive an
acknowledgement of their transmission from VIIS. All content processing and
data de-duplication will be performed by VIIS. Business partners may also
create a query message to which VIIS will generate a response message.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$29,417
|
$0
|
|
$54,240
|
$108,480
|
Nongeneral Fund
|
$196,865
|
$0
|
|
$488,160
|
$976,320
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Department of Transportation (501) -- Inventory
Module (Cardinal)
|
Jan 1, 2012
|
Dec 31, 2012
|
$4,900,000
|
|
|
Dec 31, 2013
|
|
Replace the software technology for the Web IMS application.
The current WebIMS application technology is reaching the end of its
productive life. Microsoft Corporation stopped supporting this classic Active
Server Pages software in 2008 and it is not possible to make changes to
certain sections of the application. This project will also encompass ITD
activities supporting the data exchanges between the Inventory Management
System (IMS) and the Cardinal Project FMS. This effort includes
interface design review, data mapping and validation, analysis, and Financial
Planning Division and Cardinal Project support activities carried out by ITD
related to this effort. Currently several potential data exchange
processes (interfaces) have been defined. Analysis and design tasks
will define final scope of effort.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$4,000,000
|
$0
|
|
|
$900,000
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Department of Transportation (501) -- Maintenance
Infrastructure Management System
|
Sep 1, 2011
|
Aug 1, 2014
|
$4,879,112
|
Replace the existing Asset Management System which is no
longer adequate for the increased demand for information sharing that has
come into being over the last few years. The current system does not
support many needed functions for use, which makes it more labor intensive
and error prone than the Agency can tolerate in this environment. It
was designed to be a standalone system, and now there are requests for the
data contained within. The 'Blueprint' activities over the last year
and resulting reduction in force have left VDOT with more to do with less
people. The need for more efficient and reliable system is needed.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$1,931,948
|
$178,468
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of State Police (156) -- Replacement and
Enhancement of the Central Criminal History (CCH) Application
|
Jul 9, 2012
|
Dec 31, 2015
|
$6,500,000
|
The Centralized Criminal History (CCH) application is a
component of the larger Central Criminal Records Exchange (CCRE)
system. CCH is more than 30 years old, and many of its capabilities are
based on a proprietary emulation package, which limits the Virginia State
Police (VSP) ability to use the updated infrastructure on which it
resides. The project includes purchasing of consulting services to
gather requirements and develop an implementation plan for either the
replacement or enhancement of the CCH system. Once the requirements
have been gathered, the agency will survey the market to determine whether a
suitable commercial off the shelf (COTS) package exists or whether
development will be necessary. The project also includes planning for
implementation of the system, including installation and deployment of the
software at VSP and training services for VSP staff and local agencies.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$0
|
|
$2,000,000
|
$2,000,000
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of State Police (156) -- Replacement and Enhancement
of the Statewide Incident Based Reporting System
|
Jul 9, 2012
|
Dec 31, 2013
|
$1,200,000
|
|
|
Dec 31, 2014
|
|
The project will either replace or enhance the current
statewide IBRS which operates on legacy technology and does not meet the needs
of the law enforcement community in Virginia. Consulting services will
be used to gather the requirements for the target system. Once the
requirements have been gathered, the agency will survey the market to
determine whether a suitable commercial off the shelf (COTS) package exists,
or whether development will be necessary. The project also includes
planning for implementation of the system, including installation and
deployment of the software at Virginia State Police (VSP), and training services
for VSP and the local agencies.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$0
|
|
$200,000
|
$500,000
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Secretary of Health and Human Resources (188) -- Rhapsody
Connectivity (RC)
|
Dec 30, 2011
|
Dec 2, 2012
|
$2,074,248
|
|
|
Sep 30, 2014
|
$1,656,000
|
The Orion Rhapsody data integration engine is used by DGS Department
of Consolidated Laboratory Services (DCLS) and VDH to facilitate the accurate
and secure exchange of electronic data using with the COV Enterprise Service
Bus (ESB). VDH and DCLS interfaces use Rhapsody for messaging.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$107,861
|
$0
|
|
$49,680
|
$99,360
|
Nongeneral Fund
|
$721,838
|
$0
|
|
$447,120
|
$894,240
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Virginia Department of Transportation (501) -- SharePoint
2010
|
Jan 20, 2011
|
Feb 17, 2012
|
$1,914,944
|
|
|
Completed
|
|
An upgrade will be made to the agency intranet ‘InsideVDOT’ currently
powered by Microsoft SharePoint 2003 software. Since the current software has
not been supported since 2009, an upgrade to Microsoft Office SharePoint
Server 2010 is necessary to support the added functionality.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of State Police (156) -- STARS Asset Management
Tracking System
|
May 14, 2012
|
Dec 31, 2013
|
$1,020,000
|
|
|
Jun 30, 2014
|
|
The Statewide Agencies Radio System (STARS) Program needs an asset
management and tracking system to provide up to date inventory information
and historical tracking of radio and tower assets and equipment.
Motorola, under the terms of the STARS contract, provides an inventory system
for VSP's STARS equipment. This inventory system does not provide timely
information on the STARS assets and inventory. Nor does it provide historical
tracking of assets. In addition, once 60,000 items are in the inventory,
Motorola's charges for the system will greatly increase. Currently, VSP
has over 40,000 items in inventory.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$0
|
|
$460,000
|
$560,000
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Secretary of Health and Human Resources (188) -- Syndromic
Surveillance Interface (SSI)
|
Dec 30, 2011
|
Dec 2, 2012
|
$2,639,952
|
Participating organizations create a file to include data transmitted
to the Virginia Department of Health (VDH) from facilities on a daily
basis. The data is grouped into syndromes and statistical algorithms
and are run to identify unusual temporal and geographic patterns that might
indicate situations of concern.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$34,319
|
$0
|
Nongeneral Fund
|
$229,676
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Taxation (161) -- Telephony Telephone
Replacement with VOIP
|
Dec 30, 2011
|
Aug 1, 2012
|
$1,500,000
|
|
|
May 1, 2013
|
$2,100,000
|
This project will replace the Department's current phone
system components with VOIP. This will allow the agency to eliminate
its Rockwell Phone System and adhere with VITA strategic direction.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
|
$937,000
|
|
Nongeneral Fund
|
$0
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Human Resource Management (129) -- Time,
Attendance, and Leave (TAL)
|
Dec 16, 2011
|
Oct 31, 2013
|
$966,739
|
TAL is a manual process for most Commonwealth agencies. The
responsible stewardship of state resources demands the adoption of a modern
approach to TAL. This project will automate an intensely manual process and
thereby create efficiencies and improvements in and provide statewide
economies of scale for the time and leave accounting process.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of State Police (156) -- Virginia Intelligence
Management System (VIMS)
|
Jan 3, 2012
|
Jun 28, 2013
|
$1,500,000
|
|
|
Jun 28, 2014
|
$2,500,000
|
In 2005, the Virginia Fusion Center (VFC) was formed within
Virginia State Police to focus on counter terrorism intelligence
investigations and analysis. The VFC is a joint operation between VSP
and the Virginia Department of Emergency Management (VDEM). VSP
currently operates a system for statewide intelligence, Tactical Intelligence
Processing System (TIPS). VSP plans to replace and enhance the TIPS
system since it is based on proprietary technology (Mapper) and has limited
functionality.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$0
|
$0
|
|
$1,000,000
|
$1,500,000
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Department of Corrections (799) -- Virginia CORIS
Integration with LIDS (Local Inmate Data System)
|
Nov 1, 2011
|
Dec 31, 2012
|
$1,405,400
|
|
|
Jun 30, 2013
|
$2,240,480
|
The LIDS system records offenders who enter and exit jail for
purpose of funding per diem costs in these facilities. This project
will enhance the existing Department of Corrections’ VirginiaCORIS system to
include the LIDS functionality.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
|
$1,599,280
|
|
Nongeneral Fund
|
$0
|
$0
|
Agency Name / Project Title / Description
|
Start Date
|
Completion Date
|
Estimated Project Cost
|
Jamestown-Yorktown Foundation (425) -- Yorktown Museum
Replacement Technology
|
Dec 30, 2011
|
Jun 30, 2016
|
$2,315,000
|
|
|
Dec 31, 2016
|
$2,395,000
|
This project will install the requisite technology components
for the Yorktown Museum replacement project, including exhibit technology, audio
visual components, wireless, data and telecommunications. The Yorktown
Museum Replacement project will improve the necessary IT infrastructure in
order to accommodate expected future visitation.
|
|
|
|
Estimated Project Expenditures
|
FY 2013
|
FY 2014
|
General Fund
|
$0
|
$0
|
Nongeneral Fund
|
$556,000
|
$200,000
|
|
$146,000
|
$747,000
|
2. The Health Care Reform program office has been established by
the Secretary of Health and Human Resources to address the American Recovery and
Reinvestment Act (ARRA), the Patient Protection and Patient Affordability Act
(PPACA), and the Medicaid Information Technology Architecture (MITA).
This program will be generating approximately 23 major as well as
non-major projects and the total cost of the program over seven years is
expected to be $93,043,146 with a cost to the Commonwealth of $9,773,220.
Projects will be established over the next four years. The seven year
costs include six years of operational expenses associated with the
provider incentive program that sunsets in 2021. New recurring Medicaid
expenses are also reflected in the seven year cost estimates. The
projects and cost estimates in this paragraph include efforts to modernize
eligibility determination systems within the Department of Social Services.
previous item |
next item |
new search |
table of contents | home |