SB 431 Transmission lines; utility to submit to SCC plan to install underground.

Introduced by: Jill Holtzman Vogel | all patrons    ...    notes | add to my profiles

SUMMARY AS INTRODUCED:

Underground location of transmission lines.  Requires a utility seeking State Corporation Commission approval for an extension of an existing electrical transmission line or the construction of a new line to submit to the Commission a plan to install the line underground.  Hearings on the application would be held after the Commission has reviewed the plan. The Commission shall condition its approval of an application upon the utility's agreement to install the line underground if underground installation is technologically feasible.